PROJECT NEXT STEPS
Community outreach for the project wrapped up in December 2024 and included six (6) pop-ups, six (6) workshops, a public survey with over 500 responses, and other marketing activities. After completing the community outreach, SFEI synthesized the science and research with the public feedback they received to shape the plan’s vision, goals, and objectives. In January 2025, SFEI led an implementation workshop with the City Project team, which is comprised of city staff from multiple departments including Community Services, Public Works, Sustainability, and Community Development, to discuss and identify feasible actions and metrics for the Plan. SFEI is now developing the Plan and preparing for city and public feedback on the draft plan content and recommendations.
The Biodiversity and Urban Forest Plan project schedule had to be modified to accommodate schedule revisions for other projects. This updated timeline avoids other city project overlap and accounts for internal and external review periods, advisory body meeting schedules, and city processes. Here is the new timeline:
June 2025 - City review of DRAFT Plan
Late July 2025 - Public review of DRAFT Plan
August 13, 2025 – Parks & Recreation Commission/Urban Forestry Board Mtg. to present DRAFT Plan & receive feedback
August 20, 2025 – Environmental Planning Commission Mtg. to present DRAFT Plan & receive feedback
October 8, 2025 - Parks & Recreation Commission/Urban Forestry Board Mtg. to review updated DRAFT Plan & recommend to City Council
February 24, 2026 - City Council Mtg. to present DRAFT Plan & receive feedback
April 28, 2026 - City Council Mtg. to review update DRAFT Plan & adopt